3.06.2010




Completed Plumbing, Electrical, Mechanical, Insulation, and Drywall in both the Garage and Accessory Living Quarters above; with equal rigor, manner and specifications of the Main Structure.

Ceilings and interior of closets and pantry have been primed with SAFECOAT Primercoat for new wallboard low VOC and Painted (2 Coats) SAFECOAT Flat Paint Zero VOC. Bathroom Tiles have been grouted and Hydronic Radiant System is complete and Pressure Test inspection is coming this Monday 03/08/10.

We have begun installing the Cumaru Battens (FSC Certified) - with 2 1/2" Type 316 Stainless Steel Screws @ 8" O.C. which will recieve the Exterior Muiracatiara Siding Boards (FSC Certified).