9.11.2009

We have passed Rough Framing, Electrical and Plumbing Inspections on the Main house. Next week all components and mechanical systems will be finalized; Energy Recovery Ventilators throughout the house and motion activated ceiling exhaist fans will be installed. Stanchions for the solar panels have been installed as well, along with the conduits from PV to Inverter.

The detached Garage foundations were poured into the Scaffolding Formwork with 30 % Fly Ash Concrete and waterproofed with Bentonite as in the main house, Framing and Sheathing are 90% finished, Plumbing is complete. Next week electrical comes in to wire all the Garage and Accessory Living Quarter above.