2.18.2009

Project engine starts! Sunny day and it seems like it will remain like this at least until Saturday. The plates are in place; over the trenches so the crane can drive over them. The crane and the steel are scheduled for Friday, can't wait. We have been stalled for a while with this damn weather. The condition at the jobsite are still terrible; one walks ten feet and a soil/clay cake 1" thick forms under the sole of the boots and slippery as well clay mud can be.
THIS IS ONE OF THE STEEL PLATES (8' x 10' x 1" THK.) BEING LOWERED ONTO THE TOP OF THE FOUNDATION TRENCH AT THE DETACHED GARAGE.
THIS IS THE CLEAR PATH FOR THE CRANE TO DRIVE ALL THE WAY TO WHERE THE MOMENT FRAMES ARE LOCATED.