2.26.2009

Approved city inspection today.Pouring concrete tomorow 9:30 am.  Structural engineer to inspect tomorrow at 7:30 am. All the grid lines are marked. The GluLam Column Bases will be set into place tomorrow morning.  The plumbing sleeves are inside the formwork, and all embeded  hardware poitioned. Also release agent sprayed onto formwork. Pump arrives at 8am with 200 feet of 1" rock 4" concrete hose. Concrete Trucks begin to arrive at 9:30 in 35 minute intervals 90yards total. Standard Concrete 30% Ash Class F; 3000 psi (Grade Beams and Stem Walls).